Applications Pending

81 Gardner Street

Form A, Approval Not Required (ANR)

Cathy Foskett filed a Form A Application for Endorsement of an Approval Not Required (ANR) Plan under the Subdivision Control Law to divide the property in the Residence B District into Lot 1 and Lot 2.

  1. Form A Application, filed September 3, 2026
  2. ANR Plan, dated August 28, 2026

19 Kimball Beach Road

Site Plan Review - Modification

19 Kimball Beach Road LLC filed an application to modify plans related to tree preservation and mitigation approved in connection with a Site Plan Review under § I-I of the Zoning By-Law on April 6, 2026, to reconstruct a single-family dwelling, install a new driveway and make related site improvements at 19 Kimball Beach Road in the Residence A District.

  1. Site Plan Review Modification Application, filed September 2, 2026
  2. Modification Summary Letter, received September 2, 2026
  3. Civil Plan, revised August 28, 2026
  4. Landscape Plan, revised September 1, 2026

60 Sharp Street

Special Permit A3

Sharp Street LLC and DLB Tactical. Inc. filed an application for a Special Permit A3 Parking Determination under § V-A of the Zoning By-Law to locate a health club/personal safety training facility at 60 Sharp Street in the Industrial Park South Hingham Development Overlay Districts.

  1. Special Permit A3 Application, filed August 31, 2026
  2. Layout Site Plan, revised March 18, 2008

11 Seal Cove Road

Site Plan Review

Greenman Industries Inc filed an application for Site Plan Review under § I-I of the Zoning By-Law to reconstruct a single-family dwelling, install a new driveway and make related site improvements at 11 Seal Cove Road in the Residence C District.

  1. Site Plan Review Application, filed August 13, 2026
  2. Request for Waiver Lighting Plan and Transportation Impact Assessment, received August 13, 2026
  3. Project Description, received August 13, 2026
  4. Design and Performance Standards, received August 13, 2026
  5. Grading, Drainage and Utility Plan, dated August 12, 2026
  6. Plot Plan, dated June 6, 2026
  7. Architectural Plan, revised August 10, 2026
  8. Landscape Plan, dated August 7, 2026
  9. Existing Conditions, dated June 6, 2026
  10. Neighborhood Analysis, received August 13, 2026
  11. Stormwater Report, dated August 12, 2026
  12. Architectural Plan, revised September 2, 2026
  13. Landscape Plan, dated September 2, 2026
  14. Response to Comments, dated September 5, 2026
  15. Stormwater Report, revised September 5, 2026
  16. Grading, Drainage and Utility Plan, dated September 7, 2026
  17. Response to Comments #2, dated September 8, 2026
  18. Grading, Drainage and Utility Plan, dated September 8, 2026

Peer Review

  1. P. Brennan Peer Review Report, dated August 28, 2026
  2. P. Brennan Peer Review Report, dated September 8, 2026
  3. P. Brennan Peer Review Email, dated September 9, 2026

19 Main Street

Special Permit A3

Big Day Fitness, LLC filed an application for a Special Permit A3 Parking Determination and/or Waiver under § V-A of the Zoning By-Law to locate a health club at 19 Main Street in the Business A and the Downtown Hingham Overlay Districts

  1. Special Permit A3 Application, filed August 13, 2026
  2. Big Day Fitness A3 Parking Calculation, received August 13, 2026
  3. Nearby Business Operating Hours, received August 13, 2026
  4. Parking Hour Overlap Board Summary, received August 13, 2026
  5. Hingham Sq. ALTA Survey, received August 13, 2026
  6. Board of Appeals,TCBY decision, filed November 3, 1989

40A Hersey Street

Site Plan Review

Morgan Residential LLC filed an application for Site Plan Review under § I-I of the Zoning By-Law reconstruct a single-family dwelling, including an attached garage, and make related site improvements at 40A Hersey Street in the Residence A District.

  1. Site Plan Review Application, filed July 27, 2026
  2. SPR cover letter, dated July 22, 2026
  3. Site Plans, dated July 10, 2026
  4. Architectural Plans, revised July 13, 2026
  5. Neighborhood Analysis, received July 23, 2026
  6. Stormwater Report, received July 23, 2026
  7. Response to Comments Letter, dated August 14, 2026
  8. Site Plans, revised August 14, 2026
  9. Neighborhood Summary and Photos, received August 14, 2026

Peer Review

  1. P. Brennan Peer Review Report, dated August 12, 2026
  2. P. Brennan Peer Review Report, dated August 17, 2026

33 Gardner Street

Site Plan Review

Kimberly Donlan filed an application for Site Plan Review under § I-I of the Zoning By-Law to replace an existing pool deck and install related utility, landscape, and hardscape improvements at 33 Gardner Street in the Residence B District.

  1. Site Plan Review Application, filed July 16, 2026
  2. Application Submittal Letter, filed July 16, 2026
  3. Site Plan, dated July 13, 2026
  4. Landscape Plan, dated July13, 2026.pdf
  5. Storm Water Report, dated July 13, 2026 .pdf
  6. Peer Review Response Letter, dated August 14, 2026 .pdf
  7. Site Plan, dated August 14, 2026 .pdf
  8. Storm Water Report, dated August 14, 2026 .pdf

Peer Review

  1. P. Brennan Peer Review Report, dated August 11, 2026
  2. P. Brennan Peer Review Report, dated August 17, 2026

22 Howe Street

Site Plan Review

Sean and Mairen Marshall submitted an application for Site Plan Review under § I-I of the Zoning By-Law to convert a gravel parking area to lawn; widen a paved drive; and install a 15’x21’ shed, a 35’x60’ sports court, along with landscape and hardscape improvements at 22 Howe Street in the Residence A District.

  1. Site Plan Review Application, filed July 9, 2026
  2. Existing Conditions Plan, dated June 19, 2026
  3. Site Plan, dated July 9, 2026
  4. Stormwater Report, dated July 9, 2026
  5. Landscape Plan, dated July 16, 2026
  6. Landscape Plan Rendering, dated July 16, 2026
  7. Response to Comments, dated August 3, 2026
  8. Site Plan, revised August 3, 2026
  9. Stormwater Report, revised August 3, 2026
  10. Landscape Plan, revised August 5, 2026
  11. Owners Affidavit, dated August 7, 2026
  12. Summary of Revisions, dated August 18, 2026
  13. Site Plan, dated August 18, 2026
  14. Landscape Plan, dated August 18, 2026
  15. Tree Exhibit, dated August 18, 2026
  16. Photos, received August 18, 2026
  17. Supplemental Letter, dated August 20, 2026
  18. Landscape Plan, revised August 20, 2026
  19. Tree Exhibit, dated August 20, 2026
  20. Landscape Plan revision 2, dated  August 20, 2026
  21. Landscape Rendering, revised August 20, 2026

Peer Review

  1. P. Brennan Peer Review Report, dated July 21, 2026
  2. P. Brennan Peer Review Report, dated August 4, 2026

Public Comment

  1. C. Dockendorff Public Comment, dated July 27, 2026
  2. S. Norman Public Comment, dated July 28, 2026
  3. K. and A. Gaughen Public Comment, dated August 1, 2026
  4. M. and T. Lynch Public Comment, dated August 3, 2026
  5. D. Marshall Public Comment, dated August 3, 2026
  6. M. Cox Public Comment, dated August 7, 2026
  7. C. and P. McGovern Public Comment, dated August 7, 2026
  8. J. and N. Smith Public Comment, dated August 7, 2026
  9. C. and C. Eigenmann Public Comment and Photos, dated August 7, 2026
  10. A. and K. MacLean Public Comment, dated August 7 & 8, 2026
  11. S. Gillis and T. Isgrig Public Comment, dated August 8, 2026
  12. P. and S. Lenhart Public Comment, dated August 9, 2026
  13. T. and P. Healey Public Comment, dated August 9, 2026
  14. N. and E. Morris Public Comment, dated August 8, 2026
  15. J. and N. Smith Public Comment, dated August 11, 2026
  16. C. and C. Eigenmann Public Comment, dated August 11, 2026
  17. T. Lynch Public Comment, dated August 19, 2026
  18. T. Healy Public Comment, dated August 18, 2026
  19. M. Cox Public Comment, dated August 20, 2026
  20. D. Marshall Public Comment, dated August 20, 2026
  21. M. and K. Quin Public Comment, dated August 20, 2026
  22. J. Gay Smith Public Comment, Agust 24, 2026
  23. K. and A. McLean Public Comment, dated August 24, 2026
  24. T. and P. Healey Public Comment, dated August 24, 2026

709 Main Street

Site Plan Review

Michael Ahern, Ahern Construction Management, LLC, filed an application for Site Plan Review under § I-I of the Zoning By-Law to alter and extend an existing dwelling to include an attached garage, construct a pool and pool house with an accessory dwelling unit above, and make related site improvements at 709 Main Street in the Residence B District     

  1. Site Plan Review Application, filed June 22, 2026
  2. Site Plan Review Submission Package, received June 22, 2026
  3. Contact List, received June 22, 2026
  4. Plot Plan, dated July 17, 2025
  5. Disturbance Plan, dated May 14, 2026
  6. Proposed Site Improvements, dated June 15, 2026
  7. Exhibit A and B, Existing Conditions Survey and Site Development, received June 22, 2026
  8. Architectural Plan Existing Multi Family Alteration and Addition, dated June 9, 2025
  9. Architectural Plan Pool House with ADU Above, dated June,9,2025
  10. Pool Cover Sheet and Project Data, received June 22, 2026
  11. Construction Management and Traffic Control, received June 22, 2026
  12. Stormwater Report, dated June 15, 2026
  13. Applicant Response Narrative, received July 8, 2026
  14. Existing Tree Inventory, dated  July 6, 2026
  15. Proposed Landscape Plan, dated July 6, 2026
  16. Underground Electrical and Communication Plan, dated July 5, 2026
  17. Neighborhood Gross Floor Area Ratio and Methodology, received July 8, 2026
  18. Response to Comments, dated July 21, 2026
  19. Operations and Maintenance Plan, revised July 15, 2026
  20. Proposed Site Improvements, revised July 15, 2026
  21. Applicant's Response to Abutter's Comment, dated July 27, 2026 (1)
  22. Applicant's Response to Abutter's Comment, dated July 27, 2026 (2)

Peer Review

  1. P. Brennan Peer Review Report, dated July 13, 2026
  2. P. Brennan Peer Review Report, dated July 24, 2026

Public Comment

  1. W. and K. Tollefson Public Comment, dated July 27, 2026
  2. B. and K. Fludder Public Comment, dated July 27, 2026

25 Bare Cove Park Drive (Map 69, Lot 44) 

Site Plan Review

The Town of Hingham filed an application for Site Plan Approval under § I-I of the Zoning By-Law to demolish an existing building and construct eight pickleball courts, parking area, and related improvements on a portion of 25 Bare Cove Park Drive (Map 69, Lot 44) in the Official and Open Space District.

  1. Site Plan Review Application, filed April 6, 2026
  2. Site Plan Review Application, additional signature, revision filed April, 6, 2026
  3. Letter to Planning Board, dated March 30, 2026
  4. Permit Drawings, stamped March 26, 2026
  5. Wetland Exhibit Sheet S-1, revised March 31, 2026
  6. Drainage Report, stamped March 30, 2026
  7. Traffic Report, submitted March 10, 2026
  8. Response Letter to Planning Board, dated May 11, 2026
  9. Permiting Drawings, revised May 11, 2026
  10. Drainage Report (Stamp 5.12.26), revised May 6, 2026
  11. Renderings, dated May 7, 2026
  12. Chair Recreation Committee V. Donlan Comments, dated May 15 2026

Peer Review

  1. P. Brennan Peer Review, dated April 21, 2026
  2. P. Brennan Peer Review, dated May 13, 2026

Public Comment

  1. Bare Cove Preservation, dated April 27, 2026
  2. Bare Cove Preservation, dated May 4, 2026
  3. J. Taylor, Public Comment, dated May 5, 2026
  4. G. Waters Public Comment, dated May 13, 2026
  5. M. Stack Public Comment, dated May 13, 2026
  6. H. Aborn Martin Public Comment, May 13, 2026
  7. H. Hosmer Public Comment, May 14, 2026
  8. P. Gannon Public Comment, May 14, 2026
  9. L. O'Reilly Public Comment, dated 5.14.2026
  10. D. Chisholm Public Comment, Dated May 14, 2026
  11. P. Talbot Public Comment, dated May 14, 2026
  12. R. Garrity Public Comment, dated May 18, 2026
  13. M. Reuter Public Comment, dated May 17, 2026
  14. J. Garrity Public Comment, dated May 17, 2026
  15. C. Collins Public Comment, dated May 16, 2026
  16. C. Loughlin Public Comment, dated May 16, 2026
  17. P. Bray Public Comment, dated May 16, 2026
  18. L. Donovan Public Comment, dated May 15, 2026
  19. J. Koelsch Public Comment, dated May 15, 2026
  20. B. OConnor Public Comment, dated May 15, 2026
  21. S. Delay Public Comment, dated May 15, 2026
  22. C. Hall Public Comment, dated May 15, 2026
  23. L. OReilly Public Comment, dated May 15, 2026
  24. M. Jenkins Public Comment, dated May 15, 2026
  25. P. Mosher Public Comment, dated May 15, 2026
  26. M. Bryan Public Comment, dated May 15, 2026
  27. T. Erickson Public Comment, dated May 14, 2026
  28. E. Dings Public Comment, dated May 14, 2026
  29. L. King Public Comment, dated May 14, 2026
  30. L. OReilly Public Comment, dated May 14, 2026
  31. R. Dodaro Public Comment, dated May 17, 2026
  32. Bare Cove Preservation, dated May 18, 2026
  33. W. Bryan Public Comment, dated May 15, 2026
  34. S. Hoffses Public Comment, dated May 13, 2026
  35. C. Gibson Public Comment, dated May 18, 2026
  36. J. Williams Public Comment, dated May 18, 2026

Off Bare Cove Park Drive

Site Plan Review

The Town of Hingham filed an application for Site Plan Review under § I-I, and such other relief as necessary, to construct a 26,000 SF public building and associated improvements, including driveways, parking, walkways, utilities, stormwater management and landscaping, to operate the Hingham Center for Active Living on a 5.38 acre portion of a 472.26 acre parcel (Assessor Map 77, Lot 1) located off Bare Cove Park Drive in the Official and Open Space District.

  1. Site Plan Review Application, filed December 10, 2025
  2. Site and Architectural Plans, dated December 9, 2025
  3. Stormwater Management Plan, dated December 9, 2025
  4. Post-Construction Stormwater Operation and Management Plan, dated December 9, 2025
  5. Wetlands Scientist letter re HCAL_ACEC, dated March 28, 2025
  6. Traffic Impact Report, dated December 4, 2025
  7. SLR Consulting Presentation, dated January 13, 2026
  8. Response to PGB Engineering comments (peer review), dated February 2, 2026
  9. Response to Vanasse and Associates Comments (traffic review), dated February 2, 2026
  10. Site Plan (HCAL), revised February 3, 2026
  11. Traffic Impact Study, revised January 30, 2025
  12. Stormwater Management Plan, dated February 3, 2026
  13. Post Construction Stormwater O&M Plan, dated February 3, 2026

Peer Review 

  1. J. Dirk Traffic Engineering Peer Review, dated January 2, 2026
  2. P. Brennan Civil Engineering Peer Review, dated January 9, 2026
  3. P. Brennan Civil Engineering Peer Review, dated February 3, 2026
  4. J. Dirk Traffic Engineering Peer Review, dated February 4, 2026

Public Comment

  1. F. Bianchi Public Comment, received January 10, 2026
  2. N. Correnti Public Comment, dated January 11, 2026
  3. P. Jonson Public Comment, received January 11, 2026
  4. S. Smithson Public Comment, dated January 12, 2026
  5. Y. Kanter Public Comment, dated January 12, 2026
  6. B. Rouleau Public Comment, dated January 13, 2026
  7. EcoSystem Solutions on behalf of Bare Cove Preservation LLC, Public Comment, dated January 14, 2026
  8. H Hosmer Public Comment, dated January 14, 2026 
  9. Bare Cove Preservation Public Comment, dated January 26, 2026

Land Off Old Derby Street and Whiting Street

Preliminary Subdivision

177 Old Derby Development, LLC filed an application for a Preliminary Subdivision of approximately 104 acres of land located between Old Derby Street and Whiting Street (Route 53). The proposed plan includes an extension of Old Derby Street and layout of a new connector road to Whiting Street to provide access to nine new subdivision lots. 

  1. Preliminary Subdivision Plan Application (Form B)
  2. Preliminary Subdivision Plan, dated December 2, 2025
  3. Supplemental Letter, dated February 3, 2026
  4. Preliminary Subdivision Plan, revised February 2, 2026

29 Shipyard Drive

Informal Discussion

Jumbo Capital and Toll Brothers, Inc. requested an informal meeting with the Board to discuss a potential development consisting of 52 townhomes at 29 Shipyard Drive in the Industrial District and Mixed-Use Shipyard Redevelopment Area. 

  1. Concept Sketch, dated October 18, 2024
  2. Fiscal Impact Analysis, dated June 2, 2025
  3. Presentation to the Board, dated July 28, 2025

16 & 0 Bishops Lane
Definitive Subdivision

The Young Family Trust filed a Form C application for Definitive Subdivision Plan Approval under the Subdivision Control Law and the Rules and Regulations of the Planning Board to create four residential lots to be served by a Minor Street in Residence District A.

  1. Form C Application, dated March 28, 2023
  2. Plan Set, dated March 24, 2023
  3. Waiver Requests, dated March 28, 2023
  4. Stormwater Report, dated March 24, 2023
  5. Board of Health Comments, dated March 29, 2023
  6. Conservation Officer Comments, dated May 1, 2023
  7. Town Engineer Comments, dated May 12, 2023
  8. Continuance Request, dated June 22, 2023
  9. Fire Department Improvements Memo to Fire Marshal, received July 11, 2023
  10. Updated Waiver Requests, dated July 14, 2023
  11. Response to Comments, dated July 14, 2023
  12. Site Plans, revised July 14, 2023
  13. Stormwater Report, revised July 14, 2023
  14. Fire Prevention Officer Comments, dated July 17, 2023
  15. Continuance and Extension Request, dated July 25, 2023
  16. Bishops Lane History
  17. Soil Evaluation Form, dated July 28, 2023
  18. Emergency Vehicle Turning Sketch, dated July 28, 2023
  19. Memo from Historical Administrator, dated July 20, 2023
  20. Historical Photography
  21. Preliminary Construction Schedule
  22. Response to N. Makela, dated August 14, 2023
  23. Response to Comments, received September 5, 2023
  24. Stormwater Report, revised September 1, 2023
  25. Site Plans, revised September 1, 2023
  26. Waiver Requests, revised September 5, 2023
  27. Wetland Delineation Memo, received September 5, 2023
  28. Response to P. Howell, received September 6, 2023
  29. Response to Public Comments, received September 7, 2023
  30. Fire Prevention Officer Comments, dated September 7, 2023
  31. Memo from S. Murphy, dated September 6, 2023
  32. Comments Regarding Requested Waiver, dated September 11, 2023
  33. Letter from B. Issadore, dated September 28, 2023
  34. Decision, dated October 4, 2024
  35. Defendant's Answer to Complaint, dated November 13, 2023

Public Comment

  1. Public Comment from N. Makela, dated April 30, 2023
  2. Public Comment from K. and D. Fickes, dated May 8, 2023
  3. Public Comment from K. and C. Shames, dated May 8, 2023
  4. Public Comment from W. Collins, dated May 10, 2023
  5. Public Comment from J. McGuire, dated May 10, 2023
  6. Public Comment from P. Howell, dated May 12, 2023
  7. Supplemental Photo from P. Howell
  8. Supplemental Map from P. Howell
  9. Public Comment from K. and D. Flaherty, dated May 13, 2023
  10. Public Comment from N. Perry, dated May 14, 2023
  11. Public Comment from S. Galvin, dated May 15, 2023
  12. Public Comment from K. and P. Gallacher, dated May 15, 2023
  13. Public Comment from S. Clark and C. Whitlock, received May 16, 2023
  14. Public Comment from J. and C. Gilfoy, received May 16, 2023
  15. Public Comment from E. Cornetta, received May 16, 2023
  16. Public Comment from A. and M. Bucceri, dated May 24, 2023
  17. Public Comment from B. and H. Invernizzi, dated June 14, 2023
  18. Public Comment from P. Howell, dated July 26, 2023
  19. Public Comment from N. Makela, dated July 31, 2023
  20. Public Comment from P. and D. Amster, received August 14, 2023
  21. Video from P. and D. Amster, received August 14, 2023
  22. Public Comment from V. and K. Winslow, received August 14, 2023
  23. Additional Public Comment from V. and K. Winslow, received August 14, 2023
  24. Public Comment from D. Amster, received August 23, 2023
  25. Public Comment from A. Ramirez-Jacobs, received August 28, 2023
  26. Public Comment from C. Lynch, dated August 31, 2023
  27. Public Comment from P. Howell, received September 8, 2023
  28. Supplemental Photo from P. Howell
  29. Public Comment from Fickes, Howell, Jacobs, Lynch, Makela, Ramirez-Jacobs, Shames, and Winslow, received September 8, 2023
  30. Public Comment from Fickes, Gallacher, Howell, Jacobs, Lynch, Makela, Ramirez-Jacobs, Shames, Winslow, received September 29, 2023

Peer Review

  1. J. Dirk Peer Review Report, dated May 1, 2023
  2. P. Brennan Peer Review Report, dated May 10, 2023
  3. J. Dirk Peer Review Report, dated July 24, 2023
  4. P. Brennan Peer Review Report, dated August 8, 2023
  5. P. Brennan Watershed Plan Mark-Up and Runoff Summary
  6. J. Dirk Peer Review Report, dated August 23, 2023
  7. P. Brennan Peer Review Report, dated September 6, 2023
  8. J. Dirk Peer Review Report, dated September 7, 2023